Enter Earned Quantities

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

Once Final quantities have been established, then quantities achieved to date can be entered for each Schedule Item, enabling the Earned budget to be calculated for each Schedule Item, and for each cost centre on the project.

The percentage Qty Done/FFQ (i.e. percentage complete) calculated for the Schedule Item is used to adjust the Quantity done for each sub item related to the Schedule Item, i.e. if percentage complete is 60%, then the quantity done for each sub item is changed to 60% of the FFQ for that sub item.

Earned Budget = Quantity Done/Forecast final Quantity * Current budget.

An earned budget is calculated for each sub item for the Schedule Item. Each sub item has a cost centre, so the earned budget for each cost centre is generated. This is compared with the CWIP for that cost centre to establish a productivity to date for each cost centre and the project. The Financial Status Report best shows this information.

To update Entering Earned Quantities from the Jobpac main menu, select Project > Job Setup and Reports > Schedule of Rates > SOR Job Forecasting > Enter Quantities Done..

Enter the Job number or use the Job search function to search for the required job, click OK and the following screen is displayed.

???
Field Description
Contract Quantity Current contract quantity for the Schedule Item
B/F

B : Contract Quantity EQ Forecast Final Quantity

F : Contract Quantity NE Forecast Final Quantity

Forecast Final Quantity Quantity established in the FFQ entry screen.
Qty done to date Quantity Done. Cannot be greater than FFQ.
% Complete Quantity done/FFQ
Calc SIs If this is Y, then the % complete is transferred to each sub item related to this Schedule Item. Quantities done for each sub item are adjusted using the same %.

There are four other tabs.

The Audit tab will show who last updated the Schedule Item Quantity, and the date and time.

The Variations tab will show only those Schedule Items within the Variation Section of the schedule.

The Actions menu option Detail/Summary provides detail about each Schedule Item on screen one at a time. Selecting this displays the following screen.

Note: When selected the first line on the screen is displayed, and user should use the page up/down marks to display the required Schedule Item.
???

If Schedule Item is 100% earned, the Earned budget may be less than the current budget. This is because the overhead contribution amount for Schedule Items is not included in the earned budget calculation.

If the % complete for sub items is not the same as for the Schedule Item, then sub items can be directly remeasured. To do this select the Schedule Item, and all the sub items for the Schedule Item are displayed.

The option Claimed to Qty done in the Actions menu, will copy the claimed quantities for every Schedule Item that is currently filtered on this screen. A message is displayed before this happens.

???

Copies quantities will change colour to indicate a copy has been done.

If the % complete for sub items is not the same as for the Schedule Item, then sub items can be directly remeasured. To do this select the Schedule Item, and all the sub items for the Schedule Item are displayed.

???

Changing the Quantity done for a Schedule Item or for a sub item will change the quantity to go in the forecasting worksheets, and change the forecast final cost for each cost centre associated with the change.

Field Description
B/F

B : Contract quantity EQ Forecast Final Quantity

F : Contract Quantity NE Forecast final quantity

Forecast Final Quantity Initially; the budget quantity for the sub item.
Qty done to date Quantity Done. Cannot be greater than FFQ.
% Complete Quantity done/FFQ
C If this is Y, then the line is a comment line
Actions Options Description
Detail/Summary As for the Schedule Item, this can be used to see the detail of each line item, one at a time.
Next Item/Previous Item Allows user to move to next or previous item without having to go back to the Schedule Item itself.
Expand/Contract Expands and contracts to show the full description of the sub items

Initially the sub items have the same % complete as the Schedule Item. The FFQ and Quantity Done for each sub item can be adjusted to reflect the correct measurement for that sub item, and a more accurate earned budget. On returning to the Schedule Item screen the % complete will have been recalculated to reflect the changes at the subitem level.