The screen to enter Forecast final Quantities for the Schedule Items can been configured to allow entry only of Forecast Final Quantity.
Other configurations are available via parameter FFQDEF.
To update Forecast by Item from the Jobpac main menu, select .
When the Forecast Final Quantity is selected from the menu a job selection screen is displayed. Enter the Job number or use the Job search function to search for the required job.
The following screen is displayed:

Forecast Final Quantity Entry
Only the Forecast Final Quantity (FFQ) for each Schedule Item is entered. Entering these quantities will cause the associated quantities related to the sub-items within each item to be changed by the same % value. It will also calculate the earned budget for each of these cost centres related to the individual sub items. For example, if the FFQ is 1 and this is changed to 2. Then the FFQ of all sub items (resources) will also be doubled.
The relationship between FFQ, Qty Done, and Qty to go, must be maintained. When a FFQ is changed, the Qty Done will always remain unchanged, and the Qty to go will change to maintain the relationship. This means the quantities to go in the forecasting worksheets will change. This will immediately affect the forecast final cost for cost centres.
If the Forecasting Method is SC, then the Current Contract Quantity will also change to the same value as the FFQ, with a corresponding change in budget for that item.
The Forecasting Method can be changed in this screen. The business rules associated with this change are described in the Forecasting Method section and Item Maintenance section of this manual.
Additional tabs are available displaying Sell Price, Long Description, Section, Sequence number, Tag Codes, and Variation links.
Forecast final Quantities are not entered for Parent Items, but are entered for all child items. The system automatically calculates the FFQ for a Parent Item based on the children.
The Tags Tab can be used to filter the Schedule Items, by all available codes.
The Variation Tab shows only those Schedule Items that are in the defined variation section of the schedule. It shows if the Schedule Items are linked to a variation or not.
The other options which may be available, depending parameter CPYCDQ, are:
-
Copy Qty Done to Claim Qty: Selecting this option will copy all of the Done quantities to the Claimed to date quantity in the Progress Claim screen.
-
Copy Claim Qty to Qty Done: Selecting this option will copy all current claimed to date quantities to quantities done. The Forecast Quantity to go will also be changed and Forecast Final Quantity will remain fixed.