Once forecasting of quantities has been done, and Forecasting by Item has been used to assess and change rates to complete, the forecasting status of each cost centre can be used to refine the forecast.
This is done via the BFM Contract Valuation Maintenance screen. The function may be available via a separate menu function while not in a review period. Once in a BFM review period, it is only available via the BFM Contract Valuation Maintenance screen.
Either options take the user to the same initial forecasting screen shown below.
The standard Project Managers Worksheet (PMW) Forecasting manual describes the many features in the forecasting worksheet. This manual will focus on the functions that have been added through the Schedule of Rates features.

The Last Update column is the date the last user updated the forecast for that cost centre.
The Forecasting worksheets are displayed for the selected cost centre by choosing either the PMW by Cost Centre or the PMW By Cost Code. The PMW By Cost code displays all worksheet entries for all cost types for the cost code.

Key elements on this screen are:
-
Last Upd Date Last time any of the FCC for the cost centres for this cost code were changed.
-
Head Contract Item Tab This displays the Schedule Items to which each resource line is attached.
-
Audit tab Selecting this tab displays the following screen.

The FCC for the cost centre will change during the month due to commitments being actioned, e.g. purchase orders, invoices, payroll, etc. When any changes are made to the pending lines, either by earned value quantities being entered, or a remeasure of the Schedule Items, the FCC for the cost centre is automatically updated by the sum of the worksheet entries.
-
The Last PMW Update Displays the last date/time a user updated the forecast for the cost code via either of the forecasting worksheets.
-
The Last EVB Update Displays the last date/time a user updated the forecast for the cost code via either the Forecast Final Quantity or the Earned Value options.