Forecasting by Item

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

Each Schedule Item in the schedule should be reviewed each month to establish if rates need to be changed, or new forecasting items are required to accurately forecast the cost to complete.

To update Forecast by Item from the Jobpac main menu, select Project > Job Setup and Reports > Schedule of Rates > SOR Job Forecasting > Forecasting By Item.

Enter the Job number or use the Job search function to search for the required job then click OK. The following screen is displayed.

???

Project Managers Worksheet Forecasting by Item

All of the fields on this screen are changed from other places. This represents a summary after all the previous quantity changes that have been done. The Section filter allows the user to just display a particular section.

A rate override facility is available at the Schedule Item level. This is described in the next section. The filter at the bottom of the screen enables the user to just display those Schedule Items where this feature has been used.

A number of tabs are available to display other data associated with the Schedule Items.

The tab Budget Rate shows the Original and current budget rates for each item, and also the Forecast Cost to Complete Rate (FCC Rate).

The FCC Rate for a Schedule Item is calculated by subtracting the Budget Earned to Date from the Forecast Final Cost for the Item divided by the quantity to go for the item.

The Audit tab shows the last person and date who changed the forecast by using Project Managers Worksheet (PMW) by item or PMW by cost centre, and also the last person to change the forecast via changing quantities in the Earned Budget or Forecast Final Quantity functions.

The Variations Tab shown only those items that are linked to variations.

When a Schedule Item is selected, all of the sub items (resources) required to complete that component of work are displayed.

???

The top section of the screen displays the current status of this Schedule Item

The Original Qty is that at the time of budget finalisation

The Current Qty is the current contract quantity.

The FFQ is that entered in the Forecast Final Quantity screen.

FQC is the Forecast Quantity to complete (FFQ – Quantity Done)

FCC Rate is the overall Rate to complete for the whole Schedule Item. This can be used in conjunction with the Rate Override Used indicator. This is described in the next section.

FCC is the Forecast Cost to Complete

Field Description
Line Line number. This is the link back to the originating sub item in the budget for the Schedule Item
Notes Notes that describe how the estimate or forecast was generated. These are copied from the budget when the budget was created. New forecast lines can be created in the Forecasting worksheet. This will automatically create an equivalent budget line for the Schedule Item, with a budget quantity of zero.
Resource Description Name of the resource required for this element of work.
Unit Unit of Measure
Qty to Go If Earned Budget has been done for the project, this quantity should reflect the quantity required to complete this element of work. If it is changed here, it will result in the FFQ for the element of work to be adjusted (FFQ = Qty Done + Qty to Complete)
Rate Rate to complete. (next version of this document will include Resource Library facility)
Cost Code Cost Code for this element of work.
CT Cost Type. e.g. L, M, P, S
P/C Pending or Contingency. Pending is the default. Lines can be marked as contingency components of the forecast. Jobpac will sum those lines marked C, and will present the total value of contingency in the Project Summary Report. These can be changed at any time.
C Comment indicator. 'Y' – Comment line; 'N' – Forecast line.

Each line has a number of options associated with it. These are displayed using the Right Mouse Button.

  • Extended Notes
  • Extended Resource Description
  • Delete
  • Cut
  • Copy
  • Cut to Another Item
  • Copy to Another Item
  • Paste before
  • Paste after
  • Prompt

These allow the changing of the detailed descriptions of the line item, deleting of the line, and a range of Cut and Copy options for sub items. To Paste a line, select where you want to insert the line, and use Paste Before (the line) or Paste After (the line). Prompt is cursor sensitive.

Actions Options Description
Expand/Contract Expands the description to show all lines of the description, and contracts back to one line.
Prompt Cursor sensitive. System will display a popup list related to the data where the cursor is positioned.
Add Positions the cursor at the next available position to enter a new line.
Next Tab Each click of this will take user to next tab.
Budget Makeup This displays the makeup of the cost centre budget associated with the Schedule Item. The current budget is displayed, and the option to show the original budget is available in that display.
Build From Sub items This will replace the current forecast with the current budget or original budget (user selects) for that Schedule Item. A preview is provided. To actually make the replacement, select Build From Sub items from the preview screen.
Build From History This will replace the current forecast with that of a nominated previous month. A preview is provided. To actually make the replacement, select Build From Sub items from the preview screen.
Delete All This will completely delete all lines in the worksheet for the Schedule Item.
FFQ entry Displays the FFQ screen and allows the FFQ for the Schedule Item to be changed.
Cost Centre Enquiry This is cursor sensitive. The full budget of the cost centre is displayed. All Schedule Items that makeup the cost centre budget are displayed.
Next Item Allows user to move forward to next Schedule Item without returning to Schedule Item screen.
Previous Item Allows user to move backward to previous Schedule Item without returning to Schedule Item screen.
Submit