If variations are to be used on a SOR project, then the Variation section MUST be setup in the SOR Parameter, and the project budget must be finalised.
The starting point for establishing a head contract variation is the Variation register. A variation is created in the register. It is given a number, a description, a date, and a status. Then the option Variation Buildup is used to link variation Schedule Items to the variation. The contract value of the Schedule Items is added to provide the Price for the variation. The Expected revenue field in the variation register will be defaulted to the Price. The resources for these Schedule Items combine to become the budget for the variation. Variation Schedule Items do not contribute to the contract value or budget until the variation is transferred.
To create a variation, use Variation Register. Enter the job number, and enter a variation no, or allow system to allocate the next number.

|
Field |
Description |
|---|---|
|
Description (mandatory) |
Full description of the variation. The triangle can be selected to display a drop down text box where a full description can be entered. |
|
Status (mandatory) |
Defaults to N Notified. Can be changed to required status. |
|
Date (mandatory) |
Date associated with the status. If the status is changed, then the date can be changed to match the status. |
|
Client Reference |
Document reference from the client (not mandatory) |
|
Date |
Date of client reference |
|
Site Reference |
Document reference from project |
|
Date |
Date of site reference. |
|
Proceed/Quote |
Must be marked Proceed before a variation can be transferred, or any forecasting can be done. If marked Quote, then variation cannot be transferred, and cannot be forecast. The details of resources can be viewed in the Project Managers Worksheet (PMW) by Item, but cannot be changed. |
|
Client VO Number |
The number the client has assigned to the variation. Optional |
|
Edit Client Price Submission Detail |
If status is W, Selecting the icon displays a screen where the price submission can be prepared. See Price submission below. If status is N, then this displays as Edit Client Notification Text. |
|
Price |
Sum of the contract values of the linked Schedule Items. Cannot be overridden. |
|
Expected Revenue |
Defaults to the Price, and can be overridden. It is the value the project contract is updated by if the variation is transferred before it is approved. |
|
Budget |
Sum of the budgets of all resources of linked Schedule Items. |
|
Margin |
Difference between Price and Budget if variation is approved, and difference between Expected Revenue and Budget if variation is unapproved. |
|
Allocated |
Represents the sum of the budgets of all resources of linked Schedule Items. |
|
Unallocated |
Represents the difference between the total variation budget, and the sum of budget for all resources. |
Actions options are
|
Option |
Description |
|---|---|
|
Delete |
Whole variation can be deleted if not linked to any Schedule Items. |
|
Transfer |
Used to update the contract value and budget of the project. Changes to untransfer, after variation is transferred. No changes can be made to the variation while in transferred status. |
|
Prior status |
If data exists, e.g. values, dates for prior statuses, then these will be displayed in a popup window. |
|
Variation Buildup |
This option displays all variation Schedule Items that are linked to the variation, or if no Schedule Items are linked, displays all unlinked variations. It is within this area that new variation Schedule Items can be added and linked to the variation. See Below |
|
Display Budget detail |
When Schedule Items are linked to a variation, the budget for the variation is the sum of the budget for all the linked variation Schedule Items summarised at cost centre level. This option will display the details that makes up the budget for the variation. |