Use the SOR Variation Upload process to import estimate data and manage variation preliminaries within a Schedule of Rates project.
Variation Expert Estimation Upload Parameters
Complete the parameters as follows:
| Field | Description |
|---|---|
| Job No | The Job must be a schedule of rates job and have an associated template job. |
| Upload Variation Item to Project |
Set to N for an initial load to validate all lines. Set to Y only when there are no invalid lines to update Jobpac. |
| This is a Re-Upload | Set to Y if a batch of previously uploaded variation Schedule Items is being replaced. Otherwise, set to N. |
| Start Sequence Number | Nominate the starting sequence number. The system checks for available space before the next used number. If left blank, it defaults to the last used number plus 1. |
| Evenly Spread Total OH Budget across all Schedule Items |
Set to Y to calculate item overhead based on a contribution percentage (Total OH / Total Direct Costs). Set to N to use the specific overhead values defined in the CSV file. |
| Cost Centre | Enter valid cost centres for provisional sub-items (Item Type "PS"). Only used for direct uploads from Expert Estimation. |
| Report Option | Select Spool file, PDF, or Excel. |
| View Report | Select this checkbox to preview the report on screen before printing. |
Re-Upload Criteria
- Variation Schedule Items are not linked to variations.
- No claims have been made against any of the items.
- No quantity has been recorded as "done."
During a re-upload, the user must select the items to be replaced. The system will delete existing sub-items, worksheet entries, and notes before adding the new batch.
Expert Upload Validation Report
Erroneous lines are flagged with starting error description of #ERR. If the uploaded item contract value is not the same as the calculated value and the difference is within the allowable variance defined in the system parameter EXTVAR, then a warning message will be printed. If not within the allowable variance, then an error message will be displayed. Uploaded item value is the sum of the direct cost, overhead cost and margin. Calculated item value is quantity * rate.
When there is rounding difference between the parent and sum of the child items, upload will create a rounding item where rounding item value will be set to the difference. The rounding items will be printed at the end of the report.
A Bulk Resource List will also be printed if the project is using Resource names. The report will list the following details.
- Resource Description
- Notes
- Resource Names
- Unit of Measure
- Quantity
- Rate
- Total Amount
Totals are printed at the last page of the report.
Total Overhead Budget (Schedule Item Level) is the total of the uploaded overhead.
Nominated OH (Allocated OH) is the sum of the prelim section sub item lines. Prelim section will be have section code = 9000.
Unallocated OH will be equal to the difference between Total Overhead Budget (Schedule Item Level) and Nominated OH.
Contract Sum is total of the calculated item value: Qty * rate
Direct Cost Budget is the total of the sub item lines budget.
Overhead budget is equal to the overhead budget at Schedule Item level.
Total budget is the sum of direct cost budget & overhead budget.
Margin is calculated as the difference between contract sum and total budget.
Total number of records will be printed.
Total invalid records will also be printed.
When the file is uploaded Files will be automatically be copied to the “Original State” Files.
The Schedule Item sequence number will be generated by the system. The start sequence number will be the number nominated on the upload screen. If not nominated, then the start sequence number will be the last used sequence number plus. 1. The number will be incremented by 1 for each of the succeeding Schedule Item.
The 9000 Trade/section code will be replaced by the variation preliminary section defined in the SOR parameter.
Trade/section code Schedule Items where trade/section code is not 9000, will be set to the variation section defined on the SOR parameter.
Forecasting method of provisional items will be set to RO.
Parent code of parent item will be generated starting from AA, AB, AC, AD etc. The upload will add the code to the parent code table.
Project contract sum, and margin will be not be updated. The overhead budget will be updated but the impact on the total budget will be nil.