Creating a Progress Claim

Modified: 6 Nov 2026 Jobpac Connect Job Cost Help

Select a Job number, and the following screen is displayed.

???

Claimed to Date quantities are entered in the last column. If quantities done have been entered in the Earned Value function, then these can be copied to the claimed quantities. This can be done individually or all quantities done can be copied over, or the Schedule Items can be filtered on the screen and only the filtered Schedule Items copied over.

Quantities cannot be entered for Parent items, as these are calculated as quantities are entered for the child items. There is a hidden rounding item for each parent to ensure that quantity done * rate at the parent level exactly equals the amount claimed for the parent.

Example: If the sum of the amounts claimed for the children = $1,235,784.79, and the rate for the parent was $176.89, then the system would calculate the

Quantity done to be $1,235,784.79 / $176.89 = 6986.1766635

Multiplying this back, with 4 decimal places 6,987.1767 * $176.89 = $1,235,784.80

The difference of 0.01 is held in the rounding item.

Options for Right Mouse Click are:

Sub Items

To edit/view the item’s resource names, select the required row, right-click and choose Sub Items.

Copy Qty Done

To update the item’s Claim to Date Quantity with the item’s Quantity Done just for that SOR Item, select the required row, right-click and choose Copy Qty Done.

Text

This show the Full Description of the SOR Item

Comments

Comments can be added to display under each SOR Item in the Progress Claim Report

Progress Claim Entry Functions

Progress Claim Entry functions may be accessed using the Actions menu options.

  • Next Tab
  • Expand/Contract
  • Prompt
  • Refresh
  • Clear Filters
  • Report Print
  • Variation Section
  • Copy Qty Done
  • Show/Hide Child
  • Download
  • Upload

Report Print

Use this option to print the SOR Progress Claim report. A Selection Screen is displayed.

???

Field Name Description
Job Number Defaults to current job.
Claim Number Defaults to current claim number. To print a previous Progress Claim, use the menu option
Claim Date Defaults to today’s date, and can be overridden.
Period Work Done This is the period in which the work was done. It is not the accounting period of the actual claim. It is used as the key selection in the Claim Certification Report.
GST Code Defaults to workid default output GST code
Report Level – Section, Major Heading (H), Minor Heading (h), Item Detail Defaults to Item Detail. This will show each Schedule Item on the report. Three other summary options are available. These options show one summary line for the Level option chosen.
Include Heading/Subtotal If detail report level is selected, this determines if the Section heading and subtotals appear on the report.
Include Subtotal This determines if subtotals for major and minor heading appear on the report. Defaults – Major Heading (H) level, Minor Heading (h) level
Report Type Three reports types are available, Header page, Summary Page, and the Details report. All can be produced as required. The additional option ‘Include Footer’ should be selected if a summary is to be produced at the bottom of the report. This summary includes GST and Retention.
Print Child items Default is to not print child items. If they are printed only the quantities claimed are displayed.
Print Claimed items only Default is to print all items.
Print Claimed varns only Default is to print claimed variations only
Print Variation Summary Only This will print one line per variation on report.
Ready for posting If ticked this will establish an entry in accounts receivable. This entry is not posted, or accrued. It also causes the report to be written to a claim history table with the date created. Further running of the report for the same claim number, with this option ticked will create additional versions in the history table. Providing the AR entry has not been accrued, then this entry will also be updated.

Copy Quantity Done

To copy the quantity done for all items into the Claim to Date Quantity, select Copy Qty Done from the options on the Actions menu. A new window will be opened for you to confirm the function to be done. Click Yes to proceed or No to cancel the copy function.

???

Show/Hide Child

To view/hide child values for the items, select Show/Hide Child from the options on the Actions menu.

Downloading the Progress Claim

To download the progress claim into a spreadsheet, click on the Download button above the table.

Submit