Completing a Consignment Note

Modified: 6 Nov 2026 Jobpac Connect Materials Help

When all entries have been completed, and the stock can be picked to deliver to the project, the Consignment Note must be completed.

When it is completed, the Stock values will be cleared out of the WIP account and will update Job Costs.

Select the option Complete Consignment Note from the Actions Menu.

???

User then enters the Date Completed.

???

This completes the Consignment and Displays a Consignment Note Form. Example below.

???