Skip to main content

Subcontractor Claims Paid Through Pending Invoices

Modified: 6 Nov 2026 Jobpac Connect Help

This parameter is used to indicate (Y/N) whether the claims from subcontractors will be processed through the pending invoices facility.

If the facility is used, a window of all invoices related to the subcontractor and not assigned to a Purchase Order will be displayed in the subcontract payment authorisation program to enable the selection of the invoice(s) being processed. Once the invoice is selected, that invoice will not be available for selection in the AP transaction entry program.

SCPINV

Subcontractors Claims

Y

Claims from Subcontractors will be process through the Jobpac Pending Invoices facility.

N

Claims from Subcontractors will not be processed through the Jobpac Pending Invoices facility.

Submit

Table of Contents