This function allows you to change a lump sum subcontract budget value after finalisation.
To do this, select .
To change agreement values enter a valid agreement number and note that this only applies to Lump Sum subcontracts. Press OK to continue.
Select the subcontract item you want by highlighting the line in the list, right-clicking and selecting Select or by double-clicking the line item.
Changes are made on the bottom line.
|
Field |
Description |
|---|---|
|
Amount |
Enter a budget value for the subcontract item. |
|
Budget $ |
Enter a value for the total amount of committed budget you wish to allocate. |
|
Budget % |
Represents the Budget $ allocated as a percentage of total current budget for the cost centre. |
Click OK to save your data.