- Open the Update Work In Progress screen.
-
Note the active company. If you want to change it, click
in the header and select the appropriate company.
-
In the Posting Date field, enter the posting date for the work in progress or click
to select the date from a Date Picker. The posting date is the date the work in progress affects the general ledger.
The posted, estimated, and committed costs are shown through the posting date.
- In the Control Percent Complete By field, select Cost Code.
- Click Retrieve.
- Complete the fields as described in Update Work In Progress Screen Field Reference.
- Click Save WIP Entry.