Skip to main content

Tools/Add or Edit Culvert

Modified: 13 Nov 2026 Quadri Help

When running an analysis, a "Virtual Flow Path" will move all accumulated water from the start point to the end point and continue the analysis from the latter point.

You can use it to analyze, for example, the effect of placing a culvert under a road or building a diversion ditch alongside a road.

Note: The concept does not consider dimensioning in any way. It will move all accumulated water from its start location to its end location without delay.

Add culvert

  1. Click Add Culvert. The icon is highlighted when active.
  2. Pick a start point.

    Hold Shift to enable snap.

  3. When hovering the cursor, it will display the elevation below.

    Elevation with red color is above the start point.

    Elevation with green color is below the start point.

  4. Pick your end point or next point.

    Repeat to create a polyline.

  5. Click Enter to save.

Edit culvert

  1. Select the object.
  2. Click Edit Culvert.
  3. The selected object should be in edit mode with grip points enabled.
  4. Press down your mouse button and hold the grip point, drag it to a new location, and release the mouse button.

    Repeat until all grip points are adjusted.

  5. Click Enter to save.

Workflow example

  1. The analysis shows an area of trapped water on the upside of your designed road.

  2. Create a Virtual Flow Path (culvert) with a starting point as illustrated.

  3. Find an end point on the other side of the road. A green elevation value will indicate that your end point is lower than your start point.

  4. A proposed object and location for a culvert is created.

  5. Running the analysis again shows that much of the trapped water will pass through the culvert, but not all.

  6. Deactivate the Virtual Flow tool. Select the object and select the Edit mode. Drag the grip points to a better suited location and press Enter to save.

  7. Run the Point Flow calculation again. The analysis and result should now indicate that the new location will capture most of the trapped water.

Submit

Table of Contents