The new production planning and scheduling functionalities aim to further help the production management team to plan both short-term work packages and longer-term job or sequence requirements.
Department view in work packages
There is a new department view in Tekla PowerFab Go Work Packages in Tekla PowerFab Go and in the embedded view in the Tekla PowerFab desktop app to give shop floor workers a clear, prioritized list of work packages that they should be working on in their department and location (workshop or work area).

You can select either the department view or the overview.
A progress bar has been added to show the work package completion status in the department selected.
Job No. and Work Package # columns have the same color as the work package tiles on the Production Planner.
A Total Hours column has been added.
The work package details view in Tekla PowerFab Go now contains the schedule breakdown.
This functionality was originally released in 2025 SP2.
Split a work package in Production Planner
If you are exceeding the capacity, you can split a work package to a different work area or week in the department planner view in the Production Planner.
This feature addresses the challenge of long-duration assemblies, ensuring accurate resource allocation and improved project planning for complex fabrication processes.
This feature was originally released in Tekla PowerFab 2025 SP2.
See Split a work package in Production planning in Tekla PowerFab Go.
Schedule future work packages
Scheduling capabilities in Tekla PowerFab Go Production Planner tool are now enhanced to include future work packages. This allows you to reserve capacity for upcoming projects even before they are officially issued for production.
The new tool enables both short-term and long-range planning, facilitating capacity forecasting and proactive schedule management. This helps identifying gaps in the schedule that need to be filled.
The future work packages are likely to be large blocks of work such as an entire job or sequence. The tool allows for the distribution of detailed department loadings to be split across multiple weeks and work areas.
You can create a new future work package from the Workshop Overview view in the Production Planner. You need to select an existing production control job, provide a unique name and description for the work package, and set the intended start and due dates.

You can define the required work loadings by both hours and weight required for each department within a future work package. Department-specific work can be split across multiple weeks and different work areas. During creation, work areas will be logically grouped by their associated workshops for easier selection.
Having created a new future work packages, you can easily differentiate them from regular production work packages as the future work packages have a distinct styling.

You can edit the details and capacity of a future work package.
When you add the actual production work package to the schedule, you can deduct the production work package hours and weight from existing future work package reservations, ensuring accurate capacity planning and preventing duplicate bookings.

Production planning rules
In Fabrication Maintenance, you can define production planning rules that enhance planning efficiency by helping you to assign work packages and cut lists to the most appropriate locations.


These simple rules use item attributes like shape, size, length, weight, and finish.
The rules trigger warnings when cut list or work package properties conflict with the set criteria. However, they do not prevent you from planning the work package to the location. They alert you and lead to more reliable scheduling and help prevent errors before they impact production.
The warning count for cut lists is displayed in the Warnings/Warnings # column in the Cut Lists and Work Packages dialogs. To add the column, see Customize the layout of a dialog.

Planning warnings for a work package and cut list are displayed on the Warnings tab in the Work Package and Cut Lists dialogs. For work packages, you can select to view either general or planning warnings.


The warnings are also available in Tekla PowerFab Go.
See the following:
Remote permissions: Access to cut lists and work packages
You can define access rights for cut lists and work packages for a Tekla PowerFab Go user.
In Remote Permissions, in the Cut Lists area on the Production Control/Project Management tab, you can now select workshops, machine groups, and individual machines to limit the cut lists that a particular user can see in Tekla PowerFab Go.

On the Work Packages tab, you can select workshops and work areas to limit the work packages a user can access in Tekla PowerFab Go.

Validation of department dependencies
The Production Planner in Tekla PowerFab Go now validates department dependencies based on department numbers when you schedule or reschedule work packages.
For example, a warning appears if you try to reschedule a work package task in Fabrication department (#20) after the Painting department (#30).
Week numbers in Production Planner
Week numbers have been added to the Production Planner in Tekla PowerFab Go.