Configure your preferences for purchase order numbering,
including setting custom or job number prefixes, enabling custom purchase order numbers, and
selecting the sequential counting method Trimble Materials uses to assign purchase order numbers across all projects or
within individual projects.
- On the left panel, select Settings.
- Under System Preferences, select
Orders.
- Under PO Number, set your preferences for purchase order
numbering:
- In the PO prefix default, enter any prefix you
want to automatically apply to a purchase order number when you create a
new project.
Note that any changes you make to this setting will not
affect existing projects.
- To add the project number as a prefix to all purchase orders for that
job, select Add ‘Job Number’ as a Prefix for the PO
number. Changes will be applied to projects created or
imported after you select this option.
- To enable a separate custom purchase order number to be added to each
purchase order, select Enable custom PO number. A
separate Custom PO Number field will be added to
each purchase order. The custom PO number can be any combination of
letters and numbers, and it also applies to RFQs.
If you select Enable custom PO
number:
- you can set it to be mandatory; users will be required to enter
a custom purchase order number.
- you can set it to be the primary purchase
order number. Select Use custom PO number as
primary so that it will be used on email
messages, line items, projects, and when syncing data to an ERP.
This also applies to RFQs.
- Select the method the system uses to assign numbers to purchase orders.
Under PO Counting Method, select one of the
following:
- Use sequential numbers across all
projects. When selected, purchase order numbers
will be sequentially assigned across all projects. For example,
the sequence might be 'Job#101-1' followed by 'Job#102-2'. In
the Default PO number start field, enter
the number you want purchase order numbering to start at.
- Use a sequential numbers per project.
When selected, purchase order numbers will be sequentially
assigned within each project. For example, the sequence might be
'Job#101-1' followed by 'Job#101-2' within the same project. In
the Default PO number start field, enter
the number you want purchase order numbering to start at.
- Select SAVE to apply the settings.