A project’s Bill of Materials (BoM) is designed to house your material list at the start of a project, and will give an estimate for what materials are needed and also how much they might cost. This might be referred to as your Take Off or Estimate, and will often be generated in an Excel spreadsheet or an estimating software solution. The project BoM enables effective project budgeting, seamlessly linking estimates to actual costs. By leveraging auto-calculation settings, you can streamline your workflows, ensuring accuracy and efficiency.
The BoM serves as the primary source for your budget, provided the project is set to auto-calculate the budget from the BoM. New projects have the auto-calculate budget setting enabled by default, ensuring seamless integration with the project’s budget.
See Set a project’s budget to automatically calculate from the BoM.
The BoM also provides users with a consolidated list of items to choose from when creating a requisition or material order. These items will be specific and unique to the project.
You can import a project BoM. When importing a BoM, ensure that the correct columns are mapped, and that required fields such as item name and unit of measure are filled out. Imported items can populate fields such as cost code, budget category, and UPC, streamlining the process.
You can also manually add items to a project BoM, enabling you to input unique item names and search the Company Items database for relevant items. Linking the BoM item to a Company Items database item provides benefits when adding items to an order. For example, it enables you to select, during the order workflow, the unit price from the BoM or the Company Items database for the selected item.
Items will also be automatically created in a project’s BoM if you order them for the project when they do not yet exist in the BoM, to improve tracking and reflection in the budget. When the order process is complete, the item will be added to the BoM with the price established from the associated purchase order. It will not populate an estimated quantity and will not display an estimated cost in your budget by default; you can always go back to that item, update the Estimated Quantity to best reflect what you anticipate needing to order for the entire project scope. This will then provide an Estimated Cost for the line and display in your BoM and budget.
You can initiate purchase orders or requests for quotes directly from a project BoM, with all relevant item information included in the draft purchase order.