Create an RFQ or a purchase order directly from an item (or multiple items) in a project’s BoM.
- On the left panel, select Projects.
- On the Projects page, select the name of the project you want to open.
- Select BOM.
- Select the checkbox to the left of each item you want to add to an RFQ or an order.
- At the top of the table, select either Create Order, or
Create RFQ.The New Order dialog opens.
- In the New Order dialog, from the Order
From dropdown, select the supplier or warehouse you want to
order from. For RFQs, you can select multiple options. Alternatively, if you
don’t yet know where you want to order from, select Skip supplier
selection; you can add this information later. You will need to
add it before you place the order.Note: If you do not have permission to submit an order (i.e. you only have permission to request and view orders), you will not be able to select a supplier; this must be done by the purchaser.
- Optionally, adjust the Set items quantities slider. This automatically calculates and populates item quantities based on the percentage of your total BoM. For example, if you need a third of the quantities that were estimated, set the slider to 33%; the quantities for each selected item are approximately 33% of the estimation per item. If you leave it at 100%, the purchase order/ RFQ will show the full amount.
- Select CONTINUE. A PO Draft or RFQ Draft dialog opens.
- To verify or amend any line items details, select the line item. In the dialog that opens, add or edit any required information. If the item is linked to a Company Items database item, you can choose which unit price to apply. Select the icon to the right of the Unit Price field, and in the Select Unit Price dialog, choose which unit price to use. Select APPLY. See Project Bill of Materials and Set preferences for the order creation process for additional information.