Project budgets

Modified: 14 Oct 2026 Trimble Materials Help

The project’s budget is designed to reflect your project estimate and your purchasing and billing totals, helping you track how far the job has progressed and future material orders you might anticipate.

Project Budgets are broken out by Project Phases (which can represent construction phases or spatial differentiation like floors or buildings) or Cost Codes, and Budget Categories.

Budget Categories refer to an item attribute created at the company level that helps differentiate the purpose of a cost beyond the cost code.

Project Phases, unlike Budget Categories, are unique to the project and are designed to group job costs around parameters of your choosing. Phases are created at the project level, to break financial information based on how the project is organized (for example, one phase per floor for a multi-story building).

For information on creating Budget Categories, see Set up and manage budget categories.

A project’s estimated cost amounts can be manually added to the budget, or they can be populated into the respective budget sections by connecting them to the project’s BoM.

By default, when you set up a new project, the budget is set to automatically calculate from the project’s BoM (see Set a project’s budget to automatically calculate from the BoM). The project budget will use the estimated quantities and prices of your BoM line items, as well as other populated attributes such as Budget Category and Project Phase, to populate the Estimated Cost column.

As you progress with work on the project leveraging the tools in Trimble Materials, on the Budget page, you will see the PO and invoice values start to populate into your budget.

The following information is available on a project’s Budget page:

  • Customer Estimate
  • Estimated Cost
  • CO amount. If required, a change amount can be recorded to revise the numbers in the budget.
  • Total budget = Estimated budget + CO amount
  • Invoice balance = PO amounts which are not billed
  • Invoice total = Amount of billed costs from invoices
  • PO total
  • Labor cost
  • Total cost = PO total + Labor cost
  • Paid cost
  • Budget to complete = Total budget - Invoice balance
  • % used = (Total Cost / Total Budget) x 100
Note: Hover over the i for any column to see what the calculation is for that column.
Note: You can also use the Quantities and Line Items pages to get a better understanding of what's been estimated for the project, what's been ordered, what's been received, and what's been billed. You can filter, group, and analyze this data to ensure you are conducting your project material purchasing as effectively and efficiently as possible. See Project quantities and Project line items for more information.