Skip to main content

Add project phases manually

Modified: 14 Oct 2026 Trimble Materials Help

Manually add project phases to a project in Trimble Materials.

If your Trimble Materials account is integrated with an ERP (for example, Spectrum or Vista ) or construction management software, the project phases will originate from the ERP / construction management software. You cannot edit these in Trimble Materials. However you can create additional project phases manually in Trimble Materials.

  1. On the left panel, select Projects.
  2. On the Projects page, select the name of the required project to open it.
  3. On the project details page, select Settings then select Phases.
    The Trimble Materials Phases page opens.
  4. Select the + icon to add a project phase.
  5. In the row that is added, enter a name for the phase.
  6. Repeat steps 4 and 5 to add all required phases.
Manually created project phases are added to Trimble Materials for the project.