Set a project to require 2-step order or RFQ approval

Modified: 14 Oct 2026 Trimble Materials Help

Configure a project to require a 2-step approval in the order flow for requisitions, RFQs, and purchase orders.

  1. On the left panel, select Projects.
  2. On the Projects page, select the project you want to set 2-step approval for to open it.
  3. On the Project details page, select Settings then select Setup.
  4. Select Require 2-step approval.
  5. Select SAVE.
When selected, every order for the project will need approval from two users with the appropriate approval permissions.