Skip to main content

Adjust Vendor-level Compliance Requirements

Modified: 18 Sep 2026 Trimble Pay Project Documents Help

General contractors can adjust any compliance requirement in the system.

Possible use cases for making adjustments to requirements:
  • The compliance requirement rules have changed or were set up incorrectly.
  • You need your subcontractor to get an invoice submitted, but their compliance document is not on file.
  • The subcontractor entered an incorrect date when they uploaded their document.
  1. In the left-hand sidebar, select Vendors.
    The list of vendors appears.
  2. Select the vendor.
  3. Scroll down to the Compliance Tracking section.
    The current list of compliance requirements appears.
  4. On the right-hand side of the compliance requirement row, select the pencil icon.
  5. Make the needed changes to the requirement.
  6. Select Update.
    The Update requirement window closes.
Submit

Table of Contents