Skip to main content

Begin a Flyby

Modified: 7 Jun 2026 Viewpoint Estimating Estimating Help
  1. Open a job in the Manage Earthwork Estimates screen.
    Note: To open a job in the Manage Earthwork Estimates screen, click Estimating > Earthwork > Manage Earthwork Estimates in the All Tasks pane. Click Open Existing Job. Then select the job you want to open, and click OK.
  2. Select the 3D tab, if it is not already active.
  3. In the Active Layer field on the toolbar, click to select the layer you want to flyover.
  4. Click Flyby on the speedbar.
  5. To end the flyby, click Flyby again.
Submit

Table of Contents