The yield for fill is a calculated value based on the weighted average of the yield of
cut reused as fill and the yield for any imported material.
Open a job in the Manage Earthwork Estimates
screen.
Note: To open a job in the
Manage Earthwork Estimates screen, click Estimating >
Earthwork > Manage
Earthwork Estimates in the All Tasks pane. Click Open Existing Job. Then select
the job you want to open, and click OK.
Select the Summary tab, if
it is not already active.
If you are using Boring Attributes screen, enter updated yield of individual subgrade materials and
for Import.
If you are not using
borings, enter the updated yield for the “Unclassified” material and for Import.