Copying lines is useful when you want to use the same line in different layers of a
job.
This feature enables you to copy the line or portions of the line to another layer. For
example, you could copy a line from the existing layer to the proposed layer instead of
having to digitize it again.
-
Open a job in the Manage Earthwork Estimates screen.
Note: To open a job in the Manage Earthwork Estimates screen, click in the All Tasks pane. Click Open Existing Job. Then select the job you want to open, and click
OK.
-
Select the Takeoff tab, if
it is not already active.
-
Click Select
on the speedbar.
-
Select the line you want to
copy.
-
Click Prop
on the speedbar.
-
Select the point(s) you want
to copy.
-
Click Copy.
-
Click OK.
-
In the Active
Layer field on the toolbar, click
to select the
layer for which you want to digitize a line.
-
Press Ctrl+V. The line
is copied to the layer.