Open a job in the Manage Estimates screen.
-
Open the Alternates tab.
-
Sort or arrange the alternates so they are in the appropriate order for printing.
-
Select or create an appropriate column view for the estimate. See Work with Columns for more information.
-
Click
on the quick link bar.
-
Complete the fields as described on the Printing Alternates Screen Field Reference or click Cancel to skip to the Alternate Totals Report and go to step 9.
-
Click OK.
-
Click OK. The cost items print the same way they appear on screen in the Alternates tab.
-
Complete the fields as described on the Printing Alternates Screen Field Reference .
-
Click OK.
-
Click OK.