- Open a job in the Manage Estimates screen.
- On the Alternates tab, select an alternate you want to include in the sort.
-
Click Edit
on the speedbar.
- On the Summary tab in the Sort1 field, enter the alphanumeric code for the primary sort for this alternate. If Sort1 is not displayed to the right of the field, a WBS code has been set for the sort field and you cannot manually enter a value.
- In the Sort2 field, enter the alphanumeric code for the secondary sort for this alternate. If Sort2 is not displayed to the right of the field, a WBS code has been set for the sort field and you cannot manually enter a value.
- In the Sort3 field, enter the alphanumeric code for the tertiary sort for this alternate. If Sort3 is not displayed to the right of the field, a WBS code has been set for the sort field and you cannot manually enter a value.
- Click OK.
- Repeat steps 2 - 7 for every alternate you want to include in the sort.