Skip to main content

Define the Allocation as No Allocation

Modified: 7 Sep 2026 Viewpoint Estimating Estimating Help
  1. Open a job in the Manage Estimates screen.
  2. From the Estimate tab, select the financial cost item you want to allocate.
  3. Click Edit on the speedbar.
  4. From the Cost Detail tab, click Allocate.
  5. For the Method of Allocation, select None.
  6. Click OK.
  7. Click OK.