- Open a job in the Manage Estimates screen.
-
From the Catalog tab or the
Estimate tab, click Define
on the
speedbar and select WBS Codes.
Note: Alternately, click Define
on the
speedbar and select Globals. Then click WBS
Codes. -
From the View Codes field, click
to select the WBS code for which you want to enter values.
- Click New.
- In the Code field, enter the first value for the WBS code. Note that this value can be a maximum of 10 characters.
-
Select the Auto-Increment by checkbox to create the next code by adding a specified value to the current code each time you click Add. If you select this checkbox, enter a value by which to increment.
Note: The information you entered for the previous value remains the same for the new value.
-
In the Description field, enter a text description of the value.
Note: The Quantity, Units, and Baseline fields are optional fields that enable you to calculate costs per unit and compare actual costs with baseline costs in the Summary tab.
- In the Quantity field, enter the quantity you want to apply to this value.
- In the Units field, select the appropriate unit of measure for the quantity you entered.
- In the Baseline field, enter the baseline you want to apply to this value.
- Click Notes to add additional comments to the item.
- Click Add to add the item to the WBS code.
- Repeat steps 5 - 12 until you have added the appropriate values to the WBS code.
- Click Cancel.
- Click OK.