Skip to main content

Add quantities to the Working Total

Modified: 7 Sep 2026 Viewpoint Estimating Estimating Help
  1. Open a job in the Manage Estimates screen.
  2. Open the Estimate tab.
  3. Hold Ctrl and click on any cell on each of the cost items you want to sum into the Working Total field.
  4. Right click and select Working Total > Sum. The quantities of the selected cost items are added and the total is copied to the Working Total field.
Submit