You can create a copy of a cost item. You can a new cost item by creating a copy of a cost item, then editing the copy to create a new cost item that was based on the original cost item.
- Open a job in the Manage Estimates screen.
-
From the Estimate tab, do one of the following:
Select the cost item you want to copy and click Copy
on the speedbar.Right-click on the cell and select Copy Item.
- In the Reference field, enter a different reference number. The reference in the estimate does not need to be unique. You can leave the reference set to the same as the original cost item.
- In the Description field, enter a detailed description for the duplicate cost item.
- To create a duplicate cost item with the reference and description you specified, click OK. The cost item is copied and the item appears at the bottom of the Estimate tab.