- Open a job in the Manage Estimates screen.
-
Do one of the following to open the Estimating Explorer:
Click Estimating > Tools > Estimating Explorer in the All Tasks pane.
On the Catalog tab, click Explorer
.
- In the From section, select the Estimate option button.
-
Click
to select the estimate in which you want to change the reference number the cost items.
-
Click
to expand the estimate
and do one of the following:
- Select the checkbox next to each cost item
you want to change. A checkmark
appears next to each selected item. - Select the checkbox next to a folder to
select all the cost items in a folder. A checkmark
appears next to the
folder. - Select multiple continuous cost items by
holding Shift, then selecting the first and last cost items in the group you
want to copy. A checkmark
appears next to each selected item. - Click Select to select the currently highlighted item or folder.
- If needed, click Deselect All to deselect all items and folders. Then use one of the options above to select items.
- Select the checkbox next to each cost item
you want to change. A checkmark
- In the To section, select the Estimate option button.
-
Click
to select the same estimate you selected in step 4.
- Click Move.
-
In the Modify References popup window, select one of the following options:
- None: Select this option to move the cost items without changing the reference of the cost items.
- Append to end: Select this option to move the cost items and append the value you enter to the end of each reference.
- Insert at beginning: Select this option to move the cost items and insert the value you enter to the beginning of each reference.
Important: If you move an assembly and select either the Append to end option or the Insert at beginning option, the additional information is not added to the references of the assembly members. It is only added to the assembly's reference. - Click OK.
-
To confirm changing the selected cost items, do one of the following:
Click Yes to confirm that you want to change the cost item listed. You will need to click Yes for each cost item you selected.
Click Yes To All to confirm changing all selected cost items.
- Click OK.
- Click Close.