Use the Estimating Import/Export Tool to import data through the Master Builder API using WBS codes.
To perform the import, you must have the Master Builder API running and know where the Master Builder database resides on your hard drive. Consult the Master Builder documentation for more information.
Master Builder and Viewpoint Estimating communicate using WBS codes. For the import/export process to work, you will need to configure WBS codes in Viewpoint Estimating as follows:
Bid Item
Cost Code
Division
Part Number
Phase
Task
Vendor
See WBS and UBS Codes for more information on configuring WBS codes.
Importing from Master Builder into Viewpoint Estimating will ultimately build a WBS structure in Viewpoint Estimating that will allow you to choose values given by Master Builder and apply them to WBS codes on your cost items.
To open a job in the Manage Estimates screen, click in the All Tasks pane. Then select the job you want to open, and click OK.