Set the report options

Modified: 7 Sep 2026 Viewpoint Estimating Estimating Help
  1. Open a job in the Manage Earthwork Estimates screen.
  2. Click Estimating > Earthwork > Tools > Report Options in the All Tasks pane.
  3. Complete the fields as described on the Report OptionsReport Options Screen Field Reference.
  4. If needed, click Clear to clear all information from the Header and Footer fields on the current tab.
  5. If needed, click Default to restore the default job information to the Header and Footer fields on the current tab.
    Note: If you click Clear or Default on the All Reports tab, all other tabs are updated.
  6. Click OK.