You can copy a project task into the business unit to make it available to all projects
in that business unit.
You would use this procedure if the task was created directly in the project, and you now
want to copy it into the business unit. Tasks that were originally created in the
business unit or that were one of the default business unit library tasks do not need to
be copied into the business unit.Fastpath:
- Confirm that the correct business unit is selected in the Business Unit field, and that the correct project is selected in the Project field.
-
Select .
The Project Setup - Assign - Library Tasks screen
appears.
-
(Optional) To find a specific project library task or tasks, use the
Search pane.
-
Select the Project Library Tasks checkbox.
-
Enter any additional criteria.
-
Click Search.
-
In the Project Library Tasks pane, select the checkbox
for each task you want to copy into the Business Unit Task Library.
-
Click the Copy Library Task to Library button
.
The project task is now available to be copied to any project in the business unit.