You can make a library task available on a project by assigning it to the project.

Fastpath: Project Setup > Assign > Library Tasks
  1. Confirm that the correct business unit is selected in the Business Unit field, and that the correct project is selected in the Project field.
  2. Select Project Setup > Assign > Library Tasks.
  3. In the Business Library Tasks pane (on the right), select the checkbox next to the library task you want to assign to the project and click .
The library task is now available to the project and appears in the Project Library Tasks pane on the left.