Change the prescribed order that the Tasks should be completed by changing their placement relative to one another in the Tree.
The top-to-bottom order that Tasks are listed in both Business Process templates and in Project Processes prescribes the order that the Tasks should be completed once the Process is deployed and active on a Project.
Note: The order you prescribe doesn't necessarily constrain field activity to that order.
- Confirm that the correct business unit is selected, and that the correct project is selected in the Project field.
- Choose what you want to do:
- If you want to change the order of Tasks of a Business Process template, go to the
- If you want to change the order of Tasks of a Project Process, go to the
- Select the REF number for the process.
- Drag and drop any Task:
If you haven't already done so, assign this Process to a Project.