You can set default values for project financials for a
project and copy them to your other projects. Setting defaults can save you time when you
create new Potential Change Orders (PCOs) if you want to use the same values in most
instances.
Your Markups,
Unit of Measures, Phases, and
Cost Types are imported from your ERP. For users who do not
have an ERP (Vista or Spectrum) connected to their Team instance, you can set the
following: You can also select the option to have PCO numbers
automatically generated from this screen. See Automatically Number PCOs for a Project.
- From the home page, under Projects, select the name of
the project you want to open.
Alternatively, go to the main menu

in the upper left-hand corner, select
Projects, and then select the
name of the project you want to open.
The Dashboard for the project
appears.
-
From the upper right-hand corner of the page,
select the settings icon
, then select
Project
Settings.
-
Select PCOs.
-
To add Markups, select the plus icon, then choose a cost
type and set the percentage.
Note: You can select the check box to Round to the whole
dollar.
-
To add a Units of Measure, select the plus icon and
enter the measurement and description.
-
To add a Phase, select the plus icon and enter the phase
code and description.
-
To add a Cost Type, select the plus icon and enter the
cost type code and description.
-
Select Save Changes.
The default settings for Project Financials are
updated.