Example Scenario: Project Defaults on Billable Changes

Modified: 19 Oct 2026 Vista Project Management Change Management Help

You’ve mastered the PCO, from adding items to approval, including adding vendor COs. What about billing?

Billable change orders can default with markups and add-ons from the PM Projects form. These will impact the pricing of your change order and can be overridden.
  • Project Markups - To markup different cost types by percentage, use the Markups tab on the PM Projects form. These affect individual line items. For example, $100 of estimated cost with a 10% markup is priced at $110.

    You can modify markups on the change order, but you cannot add new markups. The markup must be set up on the project before it can be added to a change order.

    Press F1 in any field on the Markups tab for more detailed information.

  • Project Add-ons - While mark-ups apply to line items, add-ons calculate as separate lines. You can view the add-ons set up on a project using the Add-ons tab on the PM Projects form.

    Your company can cause add-ons to automatically add to every new project (using the Add-ons tab on the PM Company Parameters form). On the change order, you can modify or delete the default add-ons, but an add-on must exist on the PM Projects form before it can be included in a change order.

    Press F1 in any field on the Add-ons tab for more detailed information.