You can change the post month for work completed lines in SM Work
Order Cost Posting.
Open the SM Work Orders Cost Posting form.
For each work completed
line you want to update, select the Process checkbox. If you want to select the Process checkbox for all lines, click Check All.
Note: You can use the filter bar to restrict
the records shown in the grid for easier selection. See SM Work Order Cost Posting Form for more
information.
In the Post
Month field, enter the new month and year (MM/YY) to which the
selected work completed lines will be posted.
Click Change Post
Month.
The system updates the post month to the specified month and
year in all selected lines.