Create a project with a manually entered project number by copying an existing project
When copying a project, you can copy project details (including cost types, billing formats, and budgets) from an existing project.
In the Copy From Project Posting Type field on the Cost Codes tab, click to select the posting type of the existing project.
All
Template
Standard Project
Master Project
Sub Project
In the Project to Copy From field, do one of the following:
Enter the code of the existing project you want to copy and press Tab.
Click
to select the existing project you want to copy from a Lookup List.
To copy cost codes and other related information, complete the fields as described on the Copy From Project Popup Window - Cost Codes Tab Field Reference.
To copy project billing information, complete the fields as described on the Copy From Project Popup Window - Project Billing Tab Field Reference.
To copy checklists, complete the fields as described on the Copy From Project Popup Window - Checklists Field Reference.
Click OK to return to the Project screen.