Copy Points on a Line
- Open a job in the Manage Earthwork Estimates screen.
- Select the Takeoff tab, if it is not already active.
-
In the Active Layer field, click
to select the layer that contains the line you want to copy.
-
Click Select
on the speedbar.
- Select the line for which you want to copy points.
-
Click Prop
on the speedbar.
-
Do one of the following to select the points to copy:
- Drag the stylus over the points you want to copy.
- Click on the first point, press and hold Shift, and click on the last point.
- Press Ctrl and [A] to select all.
- Click Copy.
- Click OK.
-
In the Active Layer field, click
to select the layer to which you want to copy the points.
- Press Ctrl and [V]. The points are copied to the layer as a new line with the same elevations, dimensions, and location as the original line.