Future CO / Included CO Amounts for Projections
Values displayed in the Future CO Amt and Included CO Amt columns on both the Cost and Revenue tabs in JC Override Projections will depend on how you have set the Include in Projections checkbox for the PCO’s document type (in PM Document Types) and the Projections Option for the PCO’s status code (in PM Status IDs).
- If the Include in Projections box is unchecked for the PCO’s document type, change order amounts will not be included in either the Future CO Amt or Included CO Amt columns, regardless of the Projections Option defined for the PCO’s status code.
- If the Include in Projections Option is checked and the status code’s Projections Option is:
- None, change order amounts will be excluded from the Future CO Amt and Included CO Amt columns.
- Display in Projections, change order amounts will be included in the Future CO Amt but excluded from the Included CO Amt column.
- Display & Calculate in Projections, change order amounts will be included in the Future CO Amt and Included CO Amt columns.