Financial summaries

Modified: 11 Jul 2026 ProjectSight Project Management Help

Financial summaries display the status for both contracts and invoices.

To view an AFP's financial summary, select the Financial Summary tab.

Los campos son de solo lectura.

SecciónCampoDescripción
Estado del contratoValor del contratoEl valor original del contrato. Corresponde a la suma del programa de valores (PDV) en el contrato.
Cambios a esta facturaSum of change orders for the contract, up to and including the cost period of this AFP.
Valor del contrato en este periodoRevised value of the contract for the cost period in the AFP. Calculated by adding Contract Value to Changes to this Invoice.
Valor del contrato actualRevised contract value with all change orders, including those not yet added in the AFPs. Calculated by adding all change order amounts to Contract Value.
Estado de facturaciónTotal finalizado y almacenadoTotal value of the completed work, installed material, and stored material up to and including this AFP.
Retención totalTotal amount of retainage up to and including this AFP.
Total devengado menos retenciónValue of the completed work, installed material, and stored material in all AFPs up to and including this AFP, minus retainage.
Facturas anterioresTotal billed in previous AFPs for this contract.
Monto actual a pagarAmount of payment due for the current invoice. The sum of the Net Current Due column in the AFP.
Saldo por facturarValor restante, incluida la retención, del contrato por pagar al subcontratista. Se calcula restando el Total devengado menos retención del Valor del contrato en este período.
Enviar