PM Approved CO Detail w/Est Profit
You can use the PM Approved CO Detail w/Est Profit report to show all approved changed orders for a specific contract or a range of contracts by selecting .
This report shows all approved changed orders for a specific contract or a range of contracts. It also can be run for a specific ACO or a range of ACO's. This report is run by contract so if there is more than one project pointed at a specific contract the report will show all ACO's for those projects.
|
Report Parameters |
Description |
|---|---|
|
Company |
Accept the default, or press F4 to select a company. |
|
Beginning Contract |
Press F4 to select the beginning contract for sorting. |
|
Ending Contract |
Press F4 to select the ending contract for sorting. |
|
Beginning Approved Change Order |
Select the Field Lookup button or press F4 to select the beginning approved change order. |
|
Ending Approved Change Order |
Select the Field Lookup button or press F4 to select the ending approved change order. |
|
Totals for ACO Items? |
checkbox to include totals for ACO items. |