Field Definitions: SM Rate Override Base Form
The following is a list of field descriptions for the SM Rate Override Base form. Many of the descriptions include links to other topics that provide additional information about or related to the topic.
Equipment Rates: Markup
The Equipment Rates: Markup field on the SM Rate Override Base form, Info tab.
Enter the override markup percent to apply when capturing equipment used on a work order for the customer, service site, or quote (depending on whether you accessed this form via SM Customers, SM Service Site, or SM Work Order Quotes). For example, enter 5% as 5.00000.
Leave this field blank if no override markup applies.
When entering work completed equipment lines in SM Work Orders (Work Completed tab), the system uses this percentage in conjunction with the equipment usage rate (defined for the revenue code in EM Revenue Rates by Category or EM Revenue Rates by Equipment) to derive the Billable Rate.
Labor Rates: Rate
The Labor Rates: Rate field on the SM Rate Override Base form, Info tab.
Enter the override labor rate to use when entering work completed labor lines on a work order for the customer, service site, or quote (depending on whether you accessed this form via SM Customers, SM Service Site, or SM Work Order Quotes).
Leave this field blank if no override markup applies.
When entering work completed labor lines in SM Work Orders (Work Completed tab), the system uses this rate to derive the Billable Rate.
Material Rates: Type
The Material Rates: Type drop-down on the SM Rate Override Base form, Info tab.
Specify the material rate type.
- N - No Override - Select this option if you are not overriding the base markup or discount rate defined on the rate template assigned to this service site or customer (depending on whether you accessed this form via SM Customers or SM Service Site).
- M - Markup - Select this option if the Percent specified below represents a markup rate.
- D - Discount - Select this option if the Percent specified below represents a discount rate.
The system uses the type specified here in conjunction with the Basis and Percent defined for the rate template to determine billable amounts for material-related work completed Misc, Inventory, and Purchase lines on a work order. However, this setting is only used if there are no overrides defined for a specific category or material in SM Override Category Material (accessed by selecting the Advanced button below). For more information, see Material Rate Hierarchy.
Material Rates: Basis
The Material Rates: Basis drop-down on the SM Rate Override Base form, Info tab.
This field is enabled only when the Type is M-Markup or D-Discount.
Select the rate basis to use in determining the billable rate for work completed materials on a work order for the customer, service site, or quote (depending on whether you accessed this form via SM Customers, SM Service Site, or SM Work Order Quotes).
For each of the applicable default descriptions below, IN Location Materials and HQ Materials apply as follows:
- HQ Materials — Inventory lines that reference an HQ material (that is, IN Co and Location are not specified), Purchase lines that specify a material, and Misc lines generated from AP where a material is specified.
- IN Location Materials — Work completed Inventory lines with an IN Co and Location specified.
- A-Actual Cost
- Typically used with Markups.
Select this option to use the Total Actual Cost specified on the work completed line.
This option does not apply to work completed Purchase lines; therefore if you select this option, the system will use the Total Project Cost in markup/discount calculations for Purchase lines.
- S - Standard Cost
- Typically used with Markups.
Select this option to use the standard unit cost defined for the material in HQ Materials or IN Location Materials.
This option does not apply to material-related work completed lines that do not specify a material; therefore if you select this option, the system handles the markup/discount calculations as follows:
- For work completed Misc lines that reference a material-related SM Cost Type, but do not reference a material, the system uses the Total Actual Cost.
- For work completed Purchase lines that reference a material-related SM Cost Type, but do not reference a material, the system uses the Total Projected Cost.
- V - Average Cost
- Typically used with Markups.
Select this option to use the Avg Unit Cost defined for the material in IN Location Materials.
This option does not apply for work completed lines that specify an HQ Material or do not specify a material; therefore if you select this option, the system handles the markup/discount calculations as follows:
- For lines that specify an HQ Material, the system uses the Standard Unit Cost in HQ Materials.
- For work completed Misc lines that reference a material-related SM Cost Type, but do not reference a material, the system uses the Total Actual Cost.
- For work completed Purchase lines that reference a material-related SM Cost Type, but do not reference a material, the system uses the Total Projected Cost.
- L - Last Cost
- Typically used with Markups.
Select this option to use the Last Unit Cost defined for the material in IN Location Materials.
This option does not apply for work completed lines that specify an HQ Material or do not specify a material; therefore if you select this option, the system handles the markup/discount calculations as follows:
- For lines that specify an HQ Material, the system uses the Standard Unit Cost in HQ Materials.
- For work completed Misc lines that reference a material-related SM Cost Type, but do not reference a material, the system uses the Total Actual Cost.
- For work completed Purchase lines that reference a material-related SM Cost Type, but do not reference a material, the system uses the Total Projected Cost.
- P - Standard Price
- Typically used with Discounts.
Select this option to use the standard unit price defined for the material in HQ Materials or IN Location Materials.
This option does not apply to material-related work completed lines that do not specify a material; therefore if you select this option, the system handles the markup/discount calculations as follows:
- For work completed Misc lines that reference a material-related SM Cost Type, but do not reference a material, the system uses the Total Actual Cost.
- For work completed Purchase lines that reference a material-related SM Cost Type, but do not reference a material, the system uses the Total Projected Cost
Material Rates: Break Points By
The Material Rates: Break Points By drop-down on the SM Rate Override Base form, Info tab.
Select how to apply rate break points when calculating discounts or markups for stocked or purchased materials specified on a work order using this template.
T-Total Cost - Select this option to apply rate break points based on the total cost of the material. For example if you have a break point value of $500, the system will apply a markup or discount when the material total is equal to or greater than $500.
U-Unit Cost - Select this option to apply rate break points based on the unit cost of the material. For example if you have a break point value of $10, the system will apply a markup or discount when the material's unit cost is equal to or greater than $10.
Material Rates: Percent
The Material Rates: Percent field on the SM Rate Override Base form, Info tab.
This field is enabled only when the Type is M-Markup or D-Discount.
Required.
Enter the override markup or discount percent to apply to materials specified on work completed inventory or work completed purchase lines on a work order for the customer, service site, or quote (depending on whether you accessed this form via SM Customers, SM Service Site, or SM Work Order Quotes). For example, enter 5% as 5.00000.
The system uses this rate for work completed inventory, work completed purchase lines, and work completed miscellaneous lines as follows:
- Miscellaneous lines - The system uses this rate when a material SM Cost Type is entered (that is, the cost type category is M-Material), regardless of whether you specify a material.
- Inventory lines - The system always uses this rate, even if no SM Cost Type is specified.
- Purchase lines - The system uses this rate if:
- You enter a material SM Cost Type for the PO item, regardless of whether you specify a material.
- You enter material for the PO item, but you enter a non-material SM Cost Type or leave the SM Cost Type blank.
If you override the markup/discount rate defined here by rate break point in SM Rate Override Material (accessed by selecting the Advanced button to the right), you must specify a rate here. If this rate is 0.00, the break points are ignored.
Break Points
When using break points, the system first calculates the billable rate for the work completed line using the rate specified here. It then multiplies the billable rate x quantity to derive the material total. The material total is then compared to the rate break points defined in SM Rate Override and, if a match is found, the system recalculates the billable rate using the rate break point rate. If no match is found, the previously calculated billable rate is used.
Non-Material Purchases: Markup Percent
The Non-Material Purchases: Markup Percent field on the SM Rate Override Base form, Info tab.
Enter the override markup percent to apply to non-material Misc and Purchase work completed lines on a work order for the customer, service site, or quote (depending on whether you accessed this form via SM Customers, SM Service Site, or SM Work Order Quotes). Enter 5% as 5.00000.
Leave this field blank if no override markup applies. The system will use the rate at the next level of the rate hierarchy to determine the rate to use.
Non-material work completed lines are defined as follows:
- Miscellaneous lines specifying a non-material SM Cost Type (one with a cost type category other than M-Material) with no material specified or lines were where no SM Cost Type is specified and no material is specified.
- Purchase lines with a non-material SM Cost Type or null SM Cost Type and no material specified
The system applies this rate to the Cost Rate of the work completed purchase line to determine the Billable Rate.
Enter 0.00 if no markup will be applied to non-material purchases.