How to copy a system to a new level
Not version-specific
Issue:
Stabicad
Is it possible to copy a system to a higher or lower level?
For example:
How to copy a ventilation system from level 0 to level 1 & 2.
Solution:
Steps:
- Select the system you want to copy. Hover the mouse over the system and press the tab key to select the entire system.
- Use Ctrl+C to copy the system to the clipboard.
- Click Modify -> Paste -> Aligned to selected levels to paste the system to another floor.

- Then select the desired level.

For copying Electrical installations to other levels see: Stabitip - Copy a distribution panel with circuits and consumers