PM Submittal Ball-In Court
You can use the PM Submittal Ball-In Court report to display the current status of the submittal items in the submission / approval process by selecting
.This report displays the current status of the submittal items in the submission / approval process.
There are three sections in the report:
Requesting - A submittal will display in this section if it has a Due to Responsible Firm date, but not a Sent to Responsible Firm date.
Responsible - A submittal will display in this section if it has a Sent To and Due From Responsible Firm date, but not a Received From Responsible Firm date.
Approving - A submittal will display in this section if it has a Sent To Approving Firm and Due From Approving Firm date, but not a Received From Approving Firm date. The submittal must also have a Due To / Sent To / Due From / Received From Responsible Firm date, and a Due To Approving Firm date.
Report Parameters |
Description |
---|---|
Company |
Accept the default, or press F4 to select a company. |
Project Number |
Click the Field Lookup button or press F4 to select the project (required). |
Submittal Status – empty = All |
Click the Field Lookup button or press F4 to select the submittal status or leave blank for all.. |
Group by (N)one, (S)pec Section, (R)esp Firm, (P)ackage, S(T)atus, (A)ctivity Date |
Enter N, S, R, P, T, or A. |
Sort by (S)pec Section, (R)esp Firm, (P)ackage, S(T)atus, (A)ctivity Date |
EnterS, R, P, T, or A. |
Include Closed (Y/N)? |
Enter Y or N. |
Print Notes (Y/N)? |
Enter Y or N. |