PM Subcontract Change Orders Form
Use the PM Subcontract Change Orders form to create and maintain subcontract change orders (SCOs/SubCOs).
You can also use this form to record changes in scope to an existing subcontract, such as additions or subtractions to existing items or the creation of new scope items. In addition, you can generate and send the SCO document to a list of contacts using the Create and Send feature, as well as approve the SCO.
What do you need to know?
You cannot use this form to create new subcontracts.
You can create new subcontract items using the SL Item field in the lower portion of the form. When you add items to subcontract change order, you are actually creating new subcontract (SL) items. Once you add a new SL item, you can view the new item in PM Subcontracts (Non-Interfaced tab).
You cannot create a change order for back charges or add-ons. Only subcontract items with an item type of Regular or Change can be included on a subcontract change order, which means that you cannot create change orders for subcontract items that are back charges or add-ons.
- You can remove items from a subcontract change order by highlighting the item in the lower grid and then selecting the Remove Item from SCO button (bottom of form). Removing items from a subcontract change order does not remove them from the subcontract.
Subcontract Totals
The Totals tab displays the subcontract amounts. The formulas used to calculate the totals are listed below. All of the totals on this tab include taxes.
| Total Type | Description |
|---|---|
| Original Subcontract | Original Cost + Original Tax This amount only includes regular and add-on subcontract item types. |
| Prior Approved Change Orders | A change order item must meet all of the following conditions before it will be included in this amount:
This amount does not include back charges (subcontract items with an item type of back charge). |
| Current Subcontract | Original Subcontract + Prior Approved Change Orders |
| Pending Sub CO | Total of the current SubCO including calculated tax |
| Pending Subcontract | Current Subcontract + Pending Subcontract |
| Other Pending Sub COs | Subcontract change order items must meet all of the following requirements to be included in this amount:
This amount does not include:
|
Available Estimate / Non-Interfaced / Remaining Estimate
These display-only fields are only visible in the SL items section, and show estimate information for the selected Seq/SL Item. These values are calculated as follows:
| Field | Calculation |
|---|---|
| Available Estimate | Current Estimated Cost - Actual Cost - Remaining Committed Cost + Non-Interfaced Estimated Cost |
| Non-Interfaced | This is a more complex calculation that takes a number of factors into consideration. However, in general, this calculation is the sum of the amount and taxes from PM Subcontract Detail and based on certain factors, the subtraction of some SL Item and SL Change Order detail costs (which can include taxes), plus Non-Interfaced Estimated. |
| Remaining Estimate | Available Estimate - Non-Interfaced |