Field Definitions: PM Request for Quote-66 Form
The following is a list of field descriptions for the PM Request for Quote-66 form. Many of the descriptions include links to other topics that provide additional information about or related to the topic.
Project
PCO Type
Enter the pending change order type for this RFQ. Must be a valid, active type set up in PM Document Types (with a Document Category of 'Pending Change Order').
If you accessed this form via the RFQ Distribution tab in PM Pending Change Orders, defaults the PCO Type for the active pending change order.
PCO
Enter a pending change order number or press F4 to select one from a list. This is the PCO associated with the RFQ.
You cannot use this field to create a new pending change order. You can only select an existing PCO. If you would like to create a new PCO, use the PM Pending Change Orders form.
RFQ
Create a new RFQ
There are several ways to create a new RFQ using this field:
- Enter a "+" and then press TAB. The field will populate with the next available RFQ number and create a new RFQ.
- Enter an RFQ number that has not already been set up for the selected PCO Type and PCO. The RFQ number can be up to 10 characters long. You can also press F4 to see which RFQ numbers have already been used.
- Click the New Record icon (
) and then enter a PCO type and PCO. The system will populate the RFQ field with the next available number.
Select an existing RFQ
Enter an existing RFQ number or press F4 to select it from a list.
Description
RFQ Date
Date Due
Enter the due date for this RFQ. Initially defaults a date based on the Default Standard Days Due option in PM Projects. If no ‘default days due’ specified, defaults as null.
Status
Enter the status of this RFQ, or press F4 to select one from a list.
Status codes are created and maintained in PM Status IDs .
Responsible Person
Enter the person responsible for this RFQ. Must be a valid contact set up for the ‘Project Our Firm’ specified in PM Projects or if no ‘our firm’ specified for the project, the ‘Our Firm’ specified in PM Company Parameters. This contact will be included as the person to call for information or questions regarding the change order.
Date Req'd
Specify the date by which you need this RFQ returned to you. Initially defaults a date based on the Date Sent (previous field) and the Default Standard Days Due specified in PM Projects. Due date is calculated using calendar days. If no Default Standard Days Due is specified for the project, default will be null.
The date specified here will print on the Request for Quote form.
Changes to the Date Due (Info tab) will not update this date; however, changes to the Date Sent will cause a recalculation of this date.
Response
Use this tab to enter any miscellaneous notes about this item. The space allowance is virtually unlimited.
Spelling Check
Click the Spelling icon on the toolbar or select to spell check the text in this field.
Add a Standard Note
Standard notes allow you to insert frequently used text into some fields in the application. This text is created and maintained using the HQ Standard Note form.
To insert a standard note into the field, right click the mouse while focus is in the field and select Standard Notes from the shortcut menu, which opens the Standard Note Copy window. Then enter the standard note to copy (or select from F4 lookup) and click OK. The system inserts the selected note into the field.