Use the Add-On Basis section in PM Company Add-Ons to specify the add-on basis; that is, the amount on which to base the add-on cost.
You can specify to use a flat amount or have the calculation based on a percentage of the overall change order or the total costs for a specific cost type.
If the add-on is for additional costs (e.g. bonds), you can redirect the costs to a specific phase/cost type and/or contract item. If you wish to distribute the add-on amount to all phases on the change order with a specific cost type, leave the phase blank and enter only the desired cost type. The system will distribute the add-on amount proportionally to all phases on the change order with that cost type, adjusting the last phase/cost type for rounding (if necessary).
Example:
|
Add-on: |
100 |
|
Basis: |
Cost Type |
|
Basis CT: |
1 (Labor) |
|
Percent: |
10.00 |
|
Redirect CT: |
7 (Burden) |
|
Redirect Phase: |
(blank) |
|
Pending CO: |
Phase |
CT |
Amount |
Add-on Amt |
|---|---|---|---|---|
|
02210- - |
1 |
300.00 |
30.00 |
|
|
03310- - |
1 |
300.00 |
30.00 |
|
|
04410- - |
1 |
400.00 |
40.00 |
|
|
Total: |
$1000.00 |
$100.00 |
||
|
Approved CO: |
Phase |
CT |
Amount |
|---|---|---|---|
|
02210- - |
1 |
300.00 |
|
|
7 |
30.00 |
||
|
03310- - |
1 |
300.00 |
|
|
7 |
30.00 |
||
|
04410- - |
1 |
400.00 |
|
|
7 |
40.00 |
||
|
Total: |
$1100.00 |
||