Team: Project Communications
Find definitions of the fields and measures included in the Team: Project Communications dataset organized by folder.
Daily Log Measures
- Daily Log Delays
-
This is the count of weather delays.
- Daily Log Duration Amount
-
This is the Call Log Duration in minutes.
- Daily Log Hours
-
This is the hours for the Daily log, as indicated in the Equipment and Work sections.
- Daily Log Quantity
-
This is the quantity for the Daily Log, as indicated in the Equipment and Work sections.
RFI Measures
- Count of RFIs
-
This is a count of RFIs.
- RFI Avg Days Overdue
-
The average number of days the RFI is overdue.
- RFI Avg Days to Mark as Answered
-
The average number of days for the RFI to be marked as answered.
- RFI Avg Days to Respond
-
The average number of days to respond to the RFI.
- RFI Avg Total Days for Close
-
The average number of days for the RFI to close.
- RFI Cost Impact
-
The amount by which the project cost is impacted.
- RFI Days Overdue
-
The number of days the RFI is overdue.
- RFI Days to Mark as Answered
-
The number of days to for the RFI to be marked as answered.
- RFI Days to Respond
-
The number of days to respond to the RFI.
- RFI ROM Impact
-
The rough order of magnitude by which the project cost is impacted.
- RFI Schedule Impact
-
The number of days by which the schedule is impacted.
- RFI Total Days for Close
-
The total number of days for the RFI to close.
Submittal Measures
- Count of Submittals
-
This is a count of submittals.
- Submittal Avg Days for Approval
-
The average number of days for approval.
- Submittal Avg Days for Release
-
The average number of days for release.
- Submittal Avg Days for Review
-
The average number of days for review.
- Submittal Avg Days for Submission
-
The average number of days for submission.
- Submittal Avg Days Overdue
-
The average number of days the submittal is overdue.
- Submittal Avg Total Days for Close
-
The average total number of days for the submittal to close.
- Submittal Days for Approval
-
This value is the number of days for approval.
- Submittal Days for Release
-
This value is the number of days for release.
- Submittal Days for Review
-
This value is the number of days for review.
- Submittal Days for Submission
-
This value is the number of days for submission.
- Submittal Days Overdue
-
The number of days the submittal is overdue.
- Submittal Total Days for Close
-
The total number of days for the submittal to close.
- Submittal Lead Days
-
The lead days for the submittal.
Calendar Date
- Day
-
This is the day of the month. Note that this value is based on the actual date of each record.
- Day Name
-
This is the day of the week.
- Day Name Abbreviation
-
This is the abbreviation for the day of the week.
- Month
-
Includes all dates from the start of the month through the end of the month. Note that this value is based on the actual date of each record.
- Month Name Abbreviation
-
This is the abbreviation of the month.
- Week
-
This is the week number using a 12 month calendar year. Note that this value is based on the actual date of each record.
- Week End Date
-
This the end date of each week listed by month and year.
- Week Start Date
-
This is the start date for each week listed by month and year
- Year
-
Calendar year starting with January 1st and ending on December 31st. This may be different from the company's Fiscal Calendar. Note that this value is based on the actual date of each record.
Daily Log
- Daily Log Assigned Date
-
This is the date the Daily Log was assigned.
- Daily Log Assigned to
-
This represents the contact to whom the Daily Log is assigned.
- Daily Log Completed Date
-
This is the date the Daily Log was completed.
- Daily Log Opened Date
-
This is the date the Daily Log was opened.
- Daily Log State
-
This represents the state of the Daily Log (for example,"Not Started," "In Progress," or "Completed").
- Daily Log Submitted Date
-
This is the date the Daily Log was submitted.
- Daily Log Title
-
This is the Log Title of the Daily Log.
- Daily Log Type
-
This represents the type of Daily Log. It can be either "Company Log" or "Subcontractor Log."
- Daily Log Work Summary
-
This is the work summary for the Daily Log, and may include associated dates.
Daily Log Equipment
- Daily Log Equipment Code
-
This represents the specific equipment code for the Equipment Log field.
- Daily Log Equipment Description
-
This is the description of the equipment for the Equipment Log field.
Daily Log Section
- Daily Log Section Call Time
-
This is the duration of a call in the Daily Log.
- Daily Log Section Caller
-
The is the contact listed as a caller in the Daily Log.
- Daily Log Field
-
This represents a field within a Daily Log section (for example, Weather Observations, or Work Log).
- Daily Log Field Description
-
This represents a field within a Daily Log section (for example, Weather Observations, or Work Log).
- Daily Log Section
-
This represents a Daily Log section (for example, Weather, Work, Activity).
- Daily Log Out Going Call
-
This is the out going call record listed in a Daily Log.
Daily Log Work Log Contact
- Daily Log Work Log Contact
-
This is the name of the contact indicated in the Work Log field.
Daily Log Work Log Organization
- Daily Log Work Log Organization
-
This is the name of the organization for the contact indicated in the Work Log field.
RFI
- RFI Answer Marked On
-
The date that a specific RFI was marked as answered.
- RFI Ball in Court Contact
-
The name of the contact currently assigned to the RFI.
- RFI Ball in Court Organization
-
The organization to which the current RFI assignee belongs.
- RFI Created Date
-
The date the RFI was created.
- RFI Drawing Impact
-
Indicates that the project drawings could be impacted by the information in the RFI or change made due to the RFI.
- RFI Due By
-
The due date of the RFI.
- RFI Forwarded On
-
The date the RFI was forwarded.
- RFI From Contact
-
The name of the contact sending the RFI.
- RFI From Organization
-
The organization to which the "RFI From" contact belongs.
- RFI Impact Description
-
Describes how the project schedule, ROM or cost could be impacted by the information in the RFI or change made due to the RFI.
- RFI Notes
-
The notes that have been entered for the RFI.
- RFI Number
-
This number is used to identify the RFI.
- RFI Question
-
The question that must be answered by the RFI.
- RFI Reference
-
The reference information of the RFI.
- RFI Responded On
-
The date on which the RFI was responded to.
- RFI Response
-
The actual response for the RFI.
- RFI Revision
-
The revision number of the RFI.
- RFI Sent On
-
The date on which the RFI was sent.
- RFI Spec Section
-
The specification section related to the RFI.
- RFI Status Code
-
The status code of the RFI.
- RFI Subject
-
The title or subject of the RFI.
- RFI Suggestion
-
The possible answer that has been added as a suggestion for the RFI.
- RFI To Contact
-
The name of the contact to whom the RFI is sent.
- RFI To Organization
-
The organization to which the "RFI To Contact" belongs.
- RFI Type
-
This code represents the type of RFI.
RFI State
- RFI State
-
The state of the RFI.
RFI Priority
- RFI Priority
-
The priority of the RFI.
RFI Visibility
- RFI Visibility
-
The visibility of the RFI.
Submittal
- Submittal Approved On
-
The date on which the Submittal was approved.
- Submittal Approver
-
The name of the contact approving the submittal.
- Submittal Approver Organization
-
The organization to which the submittal approver belongs.
- Submittal Assigned To
-
The name of the contact currently assigned to the submittal.
- Submittal Assigned To Organization
-
The organization to which the current submittal assignee belongs.
- Submittal Closed On
-
The date on which the submittal was closed.
- Submittal Created Date
-
The date on which the submittal was created.
- Submittal Document Type
-
The type of the submittal.
- Submittal Document Type Code
-
The code associated with the specific submittal type.
- Submittal Due From Approver
-
This is the date the submittal is due from the approver.
- Submittal Due From Submitter
-
This is the date the submittal is due from the submitter.
- Submittal Due On Site By
-
This is the date on which the submittal is due on site.
- Submittal Due To Approver
-
This is the date on which the submittal is due to the approver.
- Submittal Due To Submitter
-
This is the date on which the submittal is due to the submitter.
- Submittal Issued On
-
This is the date on which the submittal was issued.
- Submittal Issuer
-
The name of the contact issuing the submittal.
- Submittal Issuer Organization
-
The organization to which the submittal issuer belongs.
- Submittal Note
-
The text from the Note field in the submittal.
- Submittal Number
-
This number is used to identify the submittal.
- Submittal Reference
-
The reference information of the submittal.
- Submittal Rejected On
-
The date on which the submittal was rejected.
- Submittal Response
-
The response to the submittal.
- Submittal Response Code
-
The code used to indicate the response to the submittal.
- Submittal Reviewed On
-
The date on which the submittal was reviewed.
- Submittal Reviewer
-
The name of the contact reviewing the submittal.
- Submittal Reviewer Organization
-
The organization to which the submittal reviewer belongs.
- Submittal Revision
-
The revision number of the submittal.
- Submittal Submitted On
-
The date on which the submittal was submitted.
- Submittal Submitter
-
The name of the contact submitting the submittal.
- Submittal Submitter Organization
-
The organization to which the contact submitting the submitter belongs.
- Submittal Title
-
The title or subject of the submittal.
Submittal Due Date
- Submittal Due Date
-
The date the submittal is due.
- Submittal Due Date Name
-
This is the day of the week the submittal is due.
- Submittal Due Date Name Abbreviation
-
This is the abbreviation for the day of the week the submittal is due.
- Submittal Month Due
-
The month the submittal is due. Includes all dates from the start of the month through the end of the month.
- Submittal Month Due Name Abbreviation
-
This is the abbreviation for the month the submittal is due.
- Submittal Week Due
-
The week the submittal is due. This is the week number using a 12 month calendar year.
- Submittal Week Due End Date
-
The end date of the week the submittal is due. This is the week number using a 12 month calendar year.
- Submittal Week Due Start Date
-
The start date of the week the submittal is due. This is the week number using a 12 month calendar year.
- Submittal Year Due
-
The calendar year the submittal is due, starting with January 1st and ending on December 31st. This may be different from the company's Fiscal Calendar.
Submittal Package
- Submittal Package
-
The package related to the submittal.
- Submittal Package Code
-
The code associated with the submittal package.
Submittal Priority
- Submittal Priority
-
The priority of the submittal.
Submittal Spec Section
- Submittal Spec Section
-
The specification section related to the submittal.
- Submittal Spec Section
-
The description of the specification section related to the submittal.
Submittal State
- Submittal State
-
The current state of the submittal.
Submittal Visibility
- Submittal Visibility
-
The visibility of the submittal.
Team Project
- Project
-
The name of the Team project.
- Project Description
-
The description of the Team project.
- Team Project ID
-
The ID of the Team project.